Renovations Schedule (revised August 2018)
The renovations will begin in January 2018 with an expected completion in early January 2019.
Phases and Tentative Dates
Phase 1 (G/F Main Library)
January - April 2018
• Construction of Breakout Space/Leisure Study Area/Quiet Study Area
Phase 2 (G/F Main Library)
March – September 2018
• Construction of the Think Tank/Deep Quiet Study/Seminar Room/Special Collections - Needham Room/Compact Shelves Area
March - October 2018
• Construction of Social Space
Phase 3 (G/F Main Library) (<span style="font-style: italic;" "="">New)
August 2018 - early January 2019
• Renovation of the disabled / female / male washrooms