Construction of the Main Library G/F Think Tank

Banner Image

Construction of the Main Library G/F Think Tank

Renovations Schedule (revised August 2018)

The renovations will begin in January 2018 with an expected completion in early January 2019.

Phases and Tentative Dates

Phase 1 (G/F Main Library)

January - April 2018

• Construction of Breakout Space/Leisure Study Area/Quiet Study Area​

Phase 2 (G/F Main Library)

March – September 2018

• Construction of the Think Tank/Deep Quiet Study/Seminar Room/Special Collections - Needham Room/Compact Shelves Area

March - October 2018

• Construction of Social Space

Phase 3 (G/F Main Library) (<span style="font-style: italic;" "="">New)

August 2018 - early January 2019

• Renovation of the disabled / female / male washrooms

 

G/F construction phasing