Cyclical Maintenance Project

CMP banner

Cyclical Maintenance Project

Photo Status

Date of photo taken: 8/6/2015

Date of photo taken: 9/6/2015

Date of photo taken: 8/6/2015

Location: 2/F Library

Work description: Cover to the  A/C unit with mesh

Date of photo taken: 9/6/2015

  Location: West Elevation of Library

Work description: Scaffolder secured his safety harness to independent anchorage.

Date of photo taken: 13/6/2015

Date of photo taken: 13/6/2015

Date of photo taken: 13/6/2015

  Location: Roof Library

  Work description: Special training to the workers on using lifting machine.

Date of photo taken: 13/6/2015

  Location: G/F Library

  Work description: Control of  mosquitos breeding by spraying insecticide.

Date of photo taken: 16/6/2015

  Location: Near Starbucks, Library

  Work description: Site Safety Committee Meeting was held.

Date of photo taken: 19/6/2015

Location: Roof Library

Work description: The eye bolts were checked and certified by a competent person.