Renovations Schedule

The renovations will begin in January 2018 with an expected completion in late May 2018.

Tentative Dates

Phase 1 (G/F Main Library)

January - March 2018

• Construction of Breakout Space / Leisure Study Area / Quiet Study Area / The Think Tank / Deep Quiet Study Area / Discussion Room

Phase 2 (G/F Main Library)

March - May 2018

• Construction of Social Space / Special Collection / Study Room / Compact Shelves Area