Construction of the Learning Hub

Banner for Construction of the Learning Hub

Construction of the Learning Hub

Renovations Schedule (revised August 2018)

The 2/F Atrium/Exhibitions Area, temporary carrel seating, study rooms, and the seating around the Atrium on the 4/F will be temporarily closed on 28 May 2018 until completion of the 2/F renovation phases:​

  • Phase 3A – construction of the Reading Corridor / Idea Corner / SEN & AD / HD Rooms / Glass panels around the Atrium on the 4/F will be completed by early October 2018. 
  • Phase 3B – construction of the Innovation Centre / Event Corner will be completed by early January 2019

2/F floor collections and relocation:

  • ​Browsing and Po Chung collections --> Open Area on the G/F

During the renovation period, the Special Education Needs (SEN) room 420 will be temporarily relocated to Discussion Room 2, Collaboration Zone, Level 3, Main Library.

 

image of 2/F construction phase

*Subject to the lead time for the delivery of the hanging system, this phase may be realized with Phase 3B.