Renovations Schedule (revised August 2018)
The 2/F Atrium/Exhibitions Area, temporary carrel seating, study rooms, and the seating around the Atrium on the 4/F will be temporarily closed on 28 May 2018 until completion of the 2/F renovation phases:
- Phase 3A – construction of the Reading Corridor / Idea Corner / SEN & AD / HD Rooms / Glass panels around the Atrium on the 4/F will be completed by early October 2018.
- Phase 3B – construction of the Innovation Centre / Event Corner will be completed by early January 2019
2/F floor collections and relocation:
- Browsing and Po Chung collections --> Open Area on the G/F
During the renovation period, the Special Education Needs (SEN) room 420 will be temporarily relocated to Discussion Room 2, Collaboration Zone, Level 3, Main Library.
*Subject to the lead time for the delivery of the hanging system, this phase may be realized with Phase 3B.