Renovations Schedule

The renovations for the 2/F Learning Hub, Phase 3, will begin June 2018 with an expected completion in early 2019.

Tentative Dates

Phase 3 (2/F Main Library) 

Phase 3A (Jun - Sep)

  Construction of Reading Corridor / Idea Corner / WOW Space / SEN & AD / HD Rooms

• Phase 3B (Jun - Sep)

  Construction of Innovation Centre / Event Corner

Phase 3C (End Jan 2019)

  Construction of the hanging system in the WOW Space*

2F construction phase.png

*Subject to the lead time for the delivery of the hanging system, this phase may be realized with Phase 3B.